Set-up
Planning
a) The
set-up dates are scheduled by the Executive
with approximately 4 to 6 week intervals between set-ups from the
beginning of
September to the following May. Holidays and major train shows and
other events
that will draw away members are taken into consideration. These dates
are
published on the Web Site when confirmed with booking agent.
b) A
Club member is selected by the Set-up
Co-ordinator to co-ordinate the track planning process. Any member who
wishes
to try their hand at track planning should contact the Executive.
c) A
call for modules from the Track Planner will
go out about three to four weeks prior to the set-up date. Members are
encouraged to reply promptly so the track planning may begin in a
timely
fashion.
d) Two
weeks before the set-up a first draft of the
Track Plan will go out to the members listed on the Operations e-mail
list.
e) As
Operations list members make comments about
the track plan, revised versions of the plan will be periodically
published to
the Operations list for comments.
f) One
week prior to the set-up a final Track Plan
will be selected, cleaned up and sent to all members on the Members
e-mail
list. This plan will also be posted to the Web Site.
g) One
week before the set-up, a Set-up Foreman
will be selected by the Set-up Co-ordinator and the Membership informed.
h) Set-ups
generally start on the Friday evening if
the room is available. If not available, it will begin promptly at
08:00 AM on
the Saturday morning.
i) It
is desirable to have all modules delivered by
07:00 PM on the Friday evening. If unable to comply with the Friday
evening
deadline, then by 08:00 AM on the Saturday morning at the latest with
prior
arrangement with the Set-up Co-ordinator and Set-up Foreman.
j) For
special set-ups away from our normal
location, a plan and schedule will be set-up by the Set-up Co-ordinator
or
Event Co-ordinator and sent to the members.
|